Cookies

We use essential cookies to make our site work. We'd also like to set analytics cookies that help us make improvements by measuring how you use the site. These will be set only if you accept.

For more detailed information about the cookies we use, see our cookies page.

Essential Cookies

Essential cookies enable core functionality such as security, network management, and accessibility. For example, the selections you make here about which cookies to accept are stored in a cookie.

You may disable these by changing your browser settings, but this may affect how the website functions.

Analytics Cookies

We'd like to set Google Analytics cookies to help us improve our website by collecting and reporting information on how you use it. The cookies collect information in a way that does not directly identify you.

Third Party Cookies

Third party cookies are ones planted by other websites while using this site. This may occur (for example) where a Twitter or Facebook feed is embedded with a page. Selecting to turn these off will hide such content.

Skip to main content

Planned work for Marlow Bridge brought forward

By Clerk to the Parish Council Little Marlow Parish Council

Monday, 11 May 2020

ABOUT THE AUTHOR

Little Marlow Parish Council Contributor

VIEW ALL ARTICLES BY THIS AUTHOR

Press Release from Buckinghamshire Council

07 May 2020

Planned work for Marlow Bridge brought forward

Transport for Buckinghamshire (TfB) has brought forward essential planned works for Marlow’s iconic suspension bridge while traffic is at an all-time low. The work, originally due to start in September, will now begin on Monday (May 18).

Owing to the coronavirus emergency, a decision was made to split the project into two phases, and the first stage of the work will now be done in May. This will reduce the impact on residents and businesses when the current lockdown comes to an end.

Phase 1 of the project includes the cleaning of the bridge towers and repainting of its chains and hangers. This will begin at 9.30am on Monday 18 May, requiring a 24-hour road closure of the bridge until 6pm on Tuesday 26 May. The bridge will still be accessible to pedestrians and cyclists.

After this, there will be temporary two-way traffic lights in place to allow vehicles access until Friday 19 June when Phase 1 will be completed and the bridge, again, becomes fully accessible.

Phase 2 is provisionally planned to start in September and will involve repainting bridge parapets and replacing bearings on the Bisham end of the bridge.

Cabinet Member for Transport, Nick Naylor, said: “I am so pleased that we are still able to carry out this important and highly anticipated work on Marlow Bridge. Over the years, TfB has worked tirelessly to do all it can to protect and preserve this iconic structure. Now we can carry out the relevant work in a shorter time frame whilst minimising disruption to the public, which I know will be much appreciated by the residents of Marlow especially. I look forward to seeing the end result.”

TfB has a long-term strategy in place to conserve the listed bridge for current and future generations and, as part of this strategy, there is an ongoing requirement to undertake routine maintenance and refurbishment.

Contact Information

Clerk to the Parish Council

  • 01628 890301
  • 07377 424998

Find Little Marlow Parish Council

Community Office, The Pavilion, Little Marlow, Marlow, Buckinghamshire, SL7 3RS

DIRECTIONS

Additional Information

Please note that by contacting LMPC you are giving consent for the Parish Council to receive your personal details. It may be necessary to pass your details to other government agencies / Councils to answer your query. Your details will not be shared with any other third party organisations. Should you not wish your details to be shared, please indicate this in your enquiry. Please see our Privacy Statements and Data Protection Policies on our website within the publications tab.